Contract No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and Testing Work (Stage
2) Environmental
Permit no. EP-364/2009/B, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/A, FEP-08/364/2009/A
and FEP-09/364/2009/B Monthly Environmental Monitoring & Audit Report
- June 2013 -
|
CLIENTS: |
|
Civil Engineering
and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
12 July 2013 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status of Environmental Licensing and Permitting under the
Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring.
6.4 Review of the Reasons for and the Implications of
Non-compliance
6.5 Summary of action taken in the event of and follow-up on
non-compliance
7. Cumulative Construction Impact
due to the Concurrent Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects
under this Project
Table
2.2 Details of Individual Contracts
under the Project
Table
2.3 Contact Details of Key Personnel
Table
3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/01
Table
3.5 Summary of submission status
under FEP-02/364/2009
Table
3.6 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/02
Table
3.7 Summary of submission status
under FEP-01/364/2009
Table
3.8 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/18
Table
3.9 Summary of submission status
under FEP-05/364/2009/A
Table
3.10 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/15
Table
3.11 Summary of submission status
under FEP-06/364/2009/A
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.13
Summary of submission status under FEP-07/364/2009/A
Table
3.14 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2010/06
Table 3.15 Summary of submission status under
FEP-08/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.17 Summary of submission status under FEP-09/364/2009/B
Table 4.1 Noise Monitoring Stations
Table
4.2 Real Time Noise Monitoring
Stations
Table
4.3 Air Monitoring Stations
Table
5.2 Noise Monitoring Stations for
Contract no. HY/2009/18
Table
5.3 Noise Monitoring Station for
Contract no HK/2009/01 and HK/2009/02
Table
5.4 Noise Monitoring Stations for
Contract no. HY/2009/15
Table
5.5 Noise Monitoring Stations for
Contract no. HY/2009/19
Table
5.7 Real Time Noise Monitoring
Stations for Contract no. HY/2009/19
Table
5.9 Air Monitoring Stations for
Contract no. HY/2009/18
Table
5.10 Air Monitoring Station for Contract no. HK/2009/01
Table
5.11 Air Monitoring Station for Contract no. HK/2009/02
Table
5.12 Air Monitoring Station for Contract no. HY/2009/15
Table
5.13 Air Monitoring Stations for Contract no. HY/2009/19
Table
5.15 Details of Waste Disposal for
Contract no. HK/2009/01
Table
5.16 Details of Waste Disposal for
Contract no. HK/2009/02
Table
5.17 Details of Waste Disposal for
Contract no. HY/2009/18
Table
5.18 Details of Waste Disposal for
Contract no. HY/2009/15
Table
5.19 Details of Waste Disposal for Contract no. HY/2009/19
Table
5.20 Details of Waste Disposal for
Contract no. HK/2010/06
Table 5.21 Details of Waste Disposal for Contract no. HK/2012/08
Table 8.1 Summary of Environmental
Inspections for Contract no. HY/2009/15
Table
8.2 Summary of Environmental Inspections
for Contract no. HK/2009/18
Table 8.3
Summary of Environmental Inspections for Contract no. HK/2009/01
Table 8.4
Summary of Environmental Inspections for Contract no. HK/2009/02
Table
9.1 Cumulative Statistics on
Complaints
Table
9.2 Cumulative Statistics on
Successful Prosecutions
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming
month
Appendix 5.2 Noise Monitoring Results and Graphical
Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix
5.4 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification
of Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
¡P Excavation of trial pit
¡P Transplanting of trees
¡P Hoarding erection and modification
¡P Installation of couplers, UU detection,
trial trench, pre-drilling
¡P Excavation
¡P Drainage works
¡P Tunnel works
¡P Trough structure construction and associated
drilling and grouting
¡P Road works
¡P OHVD installation
¡P Pre-bored H-piling
¡P Bridges construction
¡P Scaffolding / false-work erection
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at
¡P Pre-drilling works for CWB (Stage 2).
¡P Diaphragm wall construction works at
Stage 2 (North).
¡P Temporary bulkhead wall construction
works at CH3129 (between Stage2 / Stage3).
¡P Pre-bored H piling works for CWB (Stage1b).
¡P Excavation and grouting of Pre-bored
H-pile.
¡P Pre-bored H piling works for CWB
(Stage2).
¡P Installation of dewatering well at CWB
(Stage 1 & 1b).
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
¡P Base Slab for Tunnel Portion 1
¡P Bored piles PN17 was concreted
¡P Casting Base slab for silo setup
¡P Desander setup and its mud pit
construction for D-Wall construction at Tunnel Portion 2 Ground treatment for
D-wall at WCR2 was commenced on 10 Jun 2013.
¡P Backfilling works for pipe trenches and
the road modification works along
¡P Casting of Base slab at Bay 4 of Box
Culvert N.
¡P Sheet pile cutting works at Bay5 / Bay 6
interface for subsequent construction of water plug beneath the installed
precast unit (Bay 6)
¡P Panel (BHC2) of Eastern Bulkhead Wall
was concreted
¡P Excavation for P129 and the remaining
panel of Eastern Bulkhead Wall BHC12
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
¡P ELS works and pipe roofing works at TS4
¡P Cut and cover tunnel construction at
TPCWAE
¡P Construction of
OHVD at TS1
¡P Excavation for mined tunnel
¡P Construction of Diaphragm Wall at TS2
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P Road works at
¡P Bored piling (Land)
¡P D-wall and Barrette Construction
¡P Construction works for Box Culvert T1
¡P Construction works for Culvert U1
¡P Construction of Pile cap (Land)
¡P Demolition of parapet at IEC Link
¡P Construction of dewatering well for Cut
& Cover Tunnel
¡P Removal of marine platform
¡P Construction of pile cap, column &
cross head (Marine)
¡P ELS for Cut & Cover Tunnel
¡P Laying of 1500 pipe
¡P Launching of segments
¡P Unloading segments from derrick
¡P Extraction of temporary pile from marine
section
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P Nil
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
¡P Site preparation works
¡P Site survey
¡P Hoarding erection
Noise
Monitoring
M1a and M2b: From 11 June 2013 to 14
June 2013
M3a, M4b and M5b and M6: From 11 June
2013 to 13 June 2013
Air Monitoring
24hr-TSP monitoring at CMA5a scheduled
on 21 June 2013 was temporarily suspended due to continuous electricity power
supply for 24hrs was unavailable.
1-hour and 24-hour Total Suspended
Particulates (TSP) monitoring were conducted at CMA1b ¡V Oil Street Site Office;
CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site Office Area; CMA4a
¡V Society for the Prevention of Cruelty to Animals; CMA5a - Children Garden
opposite to Pedestrian Plaza; MA1e and MA1w ¡V International Finance Centre eastern
and western wing on every six days basis.
Complaints, Notifications of Summons
and Successful Prosecutions
A follow-up joint inspection with RSS and Landscape specialist was
conducted on 10 June2013, it was considered that the withered and yellow leaves
of the affected trees (T1674,T1675,T1676,T1677,T1678,T1679,T1680,T1681,T1683,T1644,T1643,T1641,T1639)
at the concerned planter area were contributed by natural life cycle of the
affected trees and the health condition of the affected trees were considered
to be fair. It was also noted that an active CEDD works area was located within
the concerned planter area in close proximity to few of the concerned trees
(T1644, T1643, T1641, and T1639)
According
to tree inspection records from Jan 2013 to May 2013 confirmed by RSS (Document
Ref: CI-F1-043b, CI-F1-044b, CI-F1-045b, CI-F1-046b, CI-F1-047b), the affected
tree (T1712) at the concerned planter area was considered to show sign of
withering and considered to be in poor health condition in latest tree survey
report confirmed by RSS.
During
the follow-up inspection on 10 June 2013, it was observed those construction
material and oil drums were placed near the roots area of other trees within
the CEDD works. Despite the above observation, no direct evidence was found on
site which indicates the work front have contributed to the poor health
condition of the affected tree (T1712) at the time of investigation.
Nevertheless,
regular inspection to check the health condition of the trees and regular
removal of withered leaves or dead branches which deemed appropriate to maintain
the overall tree appearance were implemented by the contractor.
xxiii.
One environmental complaint under EP-364//2009/B was received on 11 June 2013 (EPD
Ref.:H04/RS/00011587-13) dated 11 June 2013) regarding noise impact near
Central Piers in the reporting month.
The
complaint reported that the noise was emanated from the construction site near
the Central Piers at around 0900 hrs on 30 May 2013 and other days and
requested follow up action by relevant department. RSS confirmed that major
noise generating construction activities undertaken at works area near Central
Pier during the concerned time include breaking up existing D-wall concrete and
excavation at portion 4B, 4C and sheet pilling works at Portion VI (
Total 1
no. of Backhoe with breaker, 1 no. of Backhoe with vibratory hammer and 4 no.s
of pneumatic breakers were deployed for the above construction activities.
Reviewing
the noise monitoring data at monitoring stations (M7e- Internation Finance
Centre Eastern End of Podium and M7w- International Finance Centre Western End
of Podium), no limit level exceedances were recorded during routine noise
monitoring event on 28 May 2013 and 03 June 2013. As similar construction works
activities conducted on 30 May 2013 was continued across the above monitoring
period, the noise emanated from the construction activities under Contract
HY/2009/18 was considered complied with the statutory requirement.
In
addition, weekly environmental site inspection was conducted on 30 May 2013 at
around 10:00. According to the inspection record, no particular observation
regarding noise impact was recorded and the mitigation measures including
erection of temporary noise barrier was observed in place.
Site Inspections and Audit
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P Excavation of trial pit
¡P Transplanting of trees
¡P Hoarding erection and modification
¡P Installation of couplers, UU detection,
trial trench, pre-drilling
¡P Excavation
¡P Drainage works
¡P Tunnel works
¡P Trough structure construction and
associated drilling and grouting
¡P Road works
¡P OHVD installation
¡P Bridges construction
¡P Scaffolding / false-work erection
¡P Profile barrier construction
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
¡P Installation of pre-bored H-pile in CWB
Stage 1B under the atrium link (from Ch80 to Ch220)
¡P Installation of pre-bored H-pile in CWB
Stage 1B under the atrium link (from Ch120 to Ch220)
¡P Construction of bulkhead Wall at Ch3129
¡P Demolition of the promenade deck and
pumping stations at HKCEC Water Channel
¡P Installation of dewatering well at CWB
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P Construction of Eastern Bulkhead wall.
¡P Wall construction at Tunnel Portion 1.
¡P D-Wall construction at Tunnel Portion 2.
¡P Rock filling and leveling stone
installation for seawall construction at both WCR4 & TWCR4.
¡P Geotextile installation for temporary
reclamation at TWCR4
¡P Precast concrete seawall installation at
WCR4 & TWCR4.
¡P Continue backfilling and road
reinstatement works at Hung Hing Road & Wan Shing Street for successful
implementation of HHR Flyover Diversion (Stage 1)
¡P Complete water plug construction works at
Bay5/Bay6 interface and commence construction of Bay 5 Box Culvert N1.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
¡P ELS works and pipe roofing works at TS4
¡P Cut and cover tunnel construction at
TPCWAE
¡P Construction of
OHVD at TS1
¡P Excavation for mined tunnel
¡P Construction of Diaphragm Wall and
Installation of King Post at TS2
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P Road works at
¡P Bored piling (Land)
¡P D-wall and Barrette Construction
¡P Construction works for Box Culvert T1
¡P Construction works for Culvert U1
¡P Construction of Pile cap (Land)
¡P Demolition of parapet at IEC Link
¡P Construction of dewatering well for Cut
& Cover Tunnel
¡P Removal of marine platform
¡P Construction of pile cap, column & cross
head (Marine)
¡P ELS for Cut & Cover Tunnel
¡P Laying of 1500f pipe
¡P Launching of segments
¡P Unloading segments from derrick
¡P Extraction of temporary pile from marine
section
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P Installation works of Precast Concrete
Box Unit
¡P Remaining works in box unit
(Installation of foam concrete)
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009/B
¡P Hoarding erection
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/B and
Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A,
FEP-08/364/2009/A and FEP-09/364/2009/B to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit
Requirements¡¨ under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/B, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009B during the period May to June 2013. The cut-off
date of reporting is at 27th of each reporting month
Section
1 Introduction ¡V
details the scope and structure of the report.
Section
2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ¡V
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ¡V summarizes the monitoring results obtained
in the reporting period.
Section
6 Compliance
Audit ¡V summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the Concurrent
Projects ¡V summarizes
the relevant cumulative construction impact due to the concurrent activities of
the concurrent Projects.
Section
8 Site Inspection ¡V
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and
¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called
¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested
2.2.1.
Design and Construction of Central ¡V Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
¡P
A dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
¡P
The Central Interchange near the Rumsey Street Flyover to provide road
connections to the Central area;
¡P
Tunnel control buildings and ventilation buildings;
¡P
Slip roads to connect the CWB to the local road system in the Wan Chai
North and
¡P
Associated road lighting, road signing, traffic control and surveillance
system; and
¡P
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2
DPs.
Table
2.1 Schedule 2 Designated
Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason
for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in
length |
DP2 |
Road P2 and other roads which are classified as
primary/district distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging
works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging
operation less than 100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter
more than 1,200 mm and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from
Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a
seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further Environmental
Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table
2.2 Details of
Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield
Depot ¡V Advanced piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at |
DP1,
DP2 |
25
August 2011 |
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East(CWB Tunnel) |
DP1 |
26
April 2011 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel ( |
DP1 |
13
July 2011 |
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link |
DP1 |
24
March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai
Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
DP works under |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587
1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912
3010 |
|
Lam Woo & CO.,
LTD. |
Contractor under Contract no. HY/2009/17 |
General Manager |
Mr. Thomas Tang |
6111 5351 |
2566
7522 |
Contractor¡¦s Representative |
Mr. Chung Man Shek |
2566 4866 |
|||
Site Agent |
Mr. Tong Au |
9725 5874 |
|||
Environmental Officer |
Dr. Priscilla Choy |
9161 7287 |
|||
Environmental Supervisor |
Mr. Tam Chun Pong |
6461 3062 |
|||
Chun Wo ¡V Leader
Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
|
2162 9909 |
2634
1626 |
Construction
Manager |
Mr. Terry Wong |
9757 9846 |
|||
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack
Chu |
9775 2467 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103
2370 |
|||
Environmental
Supervisor |
Mr. Kwong
Weng Kit |
6253
3356 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658-3002 |
2827
9996 |
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint
Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570
8013 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Mr. |
9286 9208 |
|||
Construction Manager (Marine) |
Mr. William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Mr. Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Mr. Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Mr. Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214
7700 |
|
Deputy Site Agent |
Mr. Roger Wong |
2214
7703 |
|||
Environmental Officer |
Ms. |
2823
1161 |
|||
Environmental Engineer |
Mr. Donald Yip |
2214
7721 |
|||
Environmental Engineer Graduate |
Mr. Phil Mak |
2214
7738 |
|||
Environmental Supervisor |
Mr. K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Mr. Ray Cheng |
2214 7742 |
|||
Environmental Supervisor |
Mr. K. W. Lee |
6461 4623 |
|||
Environmental Supervisor |
Mr. Ryan Tsui |
2214
7705 |
|||
Environmental Supervisor |
Mr. C. Y. Au Yeung |
6461
8631 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. K C Cheung |
2823 7813 |
2865 5229 |
Site Manager |
Mr. J.H. Chen |
3557 6368 |
2566 2192 |
||
Contractor¡¦s
Representative |
Mr. Andrew Wong |
3557
6407 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Enviromental Supervisor |
Ms. Esther Choi |
35576348 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529
2880 |
Site
Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Clement Pang |
9481 6024 |
|||
Environmental
Supervisor |
Mr.
Jacky Cheung |
9735 9200 |
|||
|
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. Andrew
TSE |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Victor
WU |
9193
8871 |
|||
Deputy
Project Manager |
Mr. George
CHEUNG |
9268
1918 |
|||
Site
Agent |
Mr. Paul
LUI |
9095
7922 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Ching
Man, CHAN |
6050
4919 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics
Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882
3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Hoarding erection and modification
¡P
Installation of couplers, UU detection, trial trench, pre-drilling
¡P
Excavation
¡P
Drainage works
¡P
Tunnel works
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
OHVD installation
¡P
Pre-bored H-piling
¡P
Bridges construction
¡P
Scaffolding / false-work erection
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
¡P
Pre-drilling works for CWB (Stage 2).
¡P
Diaphragm wall construction works at Stage 2 (North).
¡P
Temporary bulkhead wall construction works at CH3129 (between Stage2 /
Stage3).
¡P
Pre-bored H piling works for CWB (Stage1b).
¡P
Excavation and grouting of Pre-bored H-pile.
¡P
Pre-bored H piling works for CWB (Stage2).
¡P
Installation of dewatering well at CWB (Stage 1 & 1b).
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P
Base Slab for Tunnel Portion 1
¡P
Bored piles PN17 was concreted
¡P
Casting Base slab for silo setup
¡P
Desander setup and its mud pit construction for D-Wall construction at Tunnel
Portion 2 Ground treatment for D-wall at WCR2 was commenced on 10 Jun 2013.
¡P
Backfilling works for pipe trenches and the road modification works along
¡P
Casting of Base slab at Bay 4 of Box Culvert N.
¡P
Sheet pile cutting works at Bay5 / Bay 6 interface for subsequent
construction of water plug beneath the installed precast unit (Bay 6)
¡P
Panel (BHC2) of Eastern Bulkhead Wall was concreted
¡P
Excavation for P129 and the remaining panel of Eastern Bulkhead Wall
BHC12
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (
¡P
ELS works and pipe roofing works at TS4
¡P
Cut and cover tunnel construction at TPCWAE
¡P Construction of
OHVD at TS1
¡P
Excavation for mined tunnel
¡P
Construction of Diaphragm Wall at TS2
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
¡P
Road works at
¡P
Bored piling (Land)
¡P
D-wall and Barrette Construction
¡P
Construction works for Box Culvert T1
¡P
Construction works for Culvert U1
¡P
Construction of Pile cap (Land)
¡P
Demolition of parapet at IEC Link
¡P
Construction of dewatering well for Cut & Cover Tunnel
¡P
Removal of marine platform
¡P
Construction of pile cap, column & cross head (Marine)
¡P
ELS for Cut & Cover Tunnel
¡P
Laying of 1500 pipe
¡P
Launching of segments
¡P
Unloading segments from derrick
¡P
Extraction of temporary pile from marine section
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009/B
¡P
Site preparation works
¡P
Site survey
¡P
Hoarding erection
2.4.4.
In coming reporting month, the principal work activities of individual
contracts are anticipated as follows:
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P Excavation of trial pit
¡P Transplanting of trees
¡P Hoarding erection and modification
¡P Installation of couplers, UU detection,
trial trench, pre-drilling
¡P Excavation
¡P Drainage works
¡P Tunnel works
¡P Trough structure construction and
associated drilling and grouting
¡P Road works
¡P OHVD installation
¡P Bridges construction
¡P Scaffolding / false-work erection
¡P Profile barrier construction
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
¡P Installation of pre-bored H-pile in CWB
Stage 1B under the atrium link (from Ch80 to Ch220)
¡P Installation of pre-bored H-pile in CWB
Stage 1B under the atrium link (from Ch120 to Ch220)
¡P Construction of bulkhead Wall at Ch3129
¡P Demolition of the promenade deck and
pumping stations at HKCEC Water Channel
¡P Installation of dewatering well at CWB
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P Construction of Eastern Bulkhead wall.
¡P Wall construction at Tunnel Portion 1.
¡P D-Wall construction at Tunnel Portion 2.
¡P Rock filling and leveling stone
installation for seawall construction at both WCR4 & TWCR4.
¡P Geotextile installation for temporary
reclamation at TWCR4
¡P Precast concrete seawall installation at
WCR4 & TWCR4.
¡P Continue backfilling and road
reinstatement works at Hung Hing Road & Wan Shing Street for successful
implementation of HHR Flyover Diversion (Stage 1)
¡P Complete water plug construction works at
Bay5/Bay6 interface and commence construction of Bay 5 Box Culvert N1.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
¡P ELS works and pipe roofing works at TS4
¡P Cut and cover tunnel construction at
TPCWAE
¡P Construction of
OHVD at TS1
¡P Excavation for mined tunnel
¡P Construction of Diaphragm Wall and
Installation of King Post at TS2
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P Road works at
¡P Bored piling (Land)
¡P D-wall and Barrette Construction
¡P Construction works for Box Culvert T1
¡P Construction works for Culvert U1
¡P Construction of Pile cap (Land)
¡P Demolition of parapet at IEC Link
¡P Construction of dewatering well for Cut
& Cover Tunnel
¡P Construction of pile cap, column &
cross head (Marine)
¡P ELS for Cut & Cover Tunnel
¡P Laying of 1500 pipe
¡P Launching of segments
¡P Unloading segments from derrick
¡P Extraction of temporary pile from marine
section
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P Installation works of Precast Concrete
Box Unit
¡P Remaining works in box unit
(Installation of foam concrete)
Contract no. HK/2012/08 ¡V Wan Chai
Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009/B
¡P Hoarding erection
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Surrendered |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Valid |
|
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai
Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP was surrendered by the Contractor on 25 April 2013.
Contract no. 04/HY/2006 ¡V Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP was surrendered by the
Contractor on 11 February 2011.
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
3.1.5.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5
Table 3.4 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr
2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
06 Jan
2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling
equipment |
GW-RS-1293-12 |
10 Dec
2012 |
10 Dec
2012 to 9 June 2013 |
Expired |
GW-RS0166-13 |
14 Feb
2013 |
16 Feb
2013 to 13 Aug 2013 |
Valid |
|
GW-RS0310-13 |
25 Mar
2013 |
27 Mar
2013 to 25 Sept 2013 |
Valid |
|
GW-RE0274-13 |
26 Mar
2013 |
30 Mar
2013 to 29 Sept 2013 |
Valid |
|
GW-RS0274-13 |
19 Mar
2013 |
25 Mar
2013 to 24 Sep 2013 |
Valid |
|
GW-RS-0052-13 |
18 Jan
2013 |
20 Jan
2013 to 19 July 2013 |
Valid |
|
GW-RE-0371-13 |
9 Apr
2013 |
13 Apr
2013 to 12 Oct 2013 |
Valid |
|
GW-RE-0372-13 |
12 Apr
2013 |
15 Apr
2013 to 7 Oct 2013 |
Valid |
|
GW-RS0368-13 |
12 Apr
2013 |
15 Apr
2013 to 7 Oct 2013 |
Valid |
|
GW-RS1177-12 |
15 Nov
2012 |
17 Nov
2012 to10 May 2013 |
Expired |
|
GW-RS1184
-12 |
15 Nov
2012 |
17 Nov
2012 to 8 May 2013 |
Cancelled |
|
GW-RS1185-12 |
19 Nov
2012 |
21 Nov
2012 to 8 May 2013 |
Expired |
|
GW-RS1179-12 |
20 Nov
2012 |
22 Nov
2012 to 21 May 2013 |
Cancelled |
|
GW-RS1187-12 |
20 Nov
2012 |
27 Nov
2012 to 26 May 2013 |
Expired |
|
GW-RS1199-12 |
20 Nov
2012 |
26 Nov
2012 to 25 May 2013 |
Cancelled |
|
GW-RS0470-13 |
29 Apr
2013 |
9 May
2013 to 24 Oct 2013 |
Valid |
|
GW-RS0501-13 |
9 May
2013 |
11 May
2013 to 8 Nov 2013 |
Valid |
|
GW-RS0510-13 |
14 May
2013 |
15 May
2013 to 13 Nov 2013 |
Valid |
|
GW-RS0579-13 |
29 May
2013 |
29 May
2013 to 26 Nov 2013 |
Valid |
|
GW-RS0626-13 |
13 Jun
2013 |
15 Jun
2013 to 12 Dec 2013 |
Valid |
|
GW-RS0631-13 |
14 Jun
2013 |
14 Jun
2013 to 13 Dec 2013 |
Valid |
|
GW-RS0651-13 |
21 Jun
2013 |
22 Jun
2013 to 20 Dec 2013 |
Valid |
|
Discharge
Licence |
WT00009641-2011 |
24 Jul
2011 |
31 Jul
2016 |
Valid |
WT00006220-2010 |
18 Mar
2010 |
31 Mar 2015 |
Valid |
|
Billing account under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration
as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan
2010 |
N/A |
Valid |
Table 3.5 Summary of submission
status under FEP-02/364/2009
EP Condition |
Submission |
Date
of
Submission |
Special
Conditions, Clause 2.7 & 2.8 |
Works
Schedule and Location Plan |
18 May
2011 |
Special
Conditions, Clause 2.6 |
Environmental
Management Organization Chart |
18 May
2011 |
Special
Conditions, Clause 2.6 |
Commencement
Date of Works |
20 Jun 2011 |
Special
Conditions, Clause 2.9 |
Noise
Management Plan |
10
Jun 2011 |
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.6.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.
Table 3.6 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS1038-12 |
10 Oct 2012 |
10 Oct 2012 to 9 Apr
2013 |
Valid |
GW-RS1223-12 |
27 Nov 2012 |
7 Dec 2012 to 5 June 2013 |
Expired |
|
GW-RS1243-12 |
3 Dec 2012 |
5 Dec 2012 to 29 May 2013 |
Expired |
|
GW-RE1055-12 |
30 Nov 2012 |
3 Dec 2012 to 29 May 2013 |
Valid |
|
GW-RS1228-12 |
30 Nov 2012 |
30 Nov 2012 to 29 May 2013 |
Expired |
|
GW-RS1363-12 |
24 Dec 2012 |
9 Jan 2013 to 7 July 2013 |
Cancelled |
|
GW-RS1381-12 |
31 Dec
2012 |
9 Jan 2013 to 7 July 2013 |
Valid |
|
GW-RS1384-12 |
31 Dec
2012 |
17 Jan 2013 to 16 July 2013 |
Valid |
|
GW-RS0206-13 |
22 Feb 2013 |
24 Feb 2013 to 19 Aug 2013 |
Valid |
|
GW-RS0061-13 |
17 Jan 2013 |
1 Feb 2013 to 31 July 2013 |
Cancelled |
|
GW-RS0062-13 |
17 Jan 2013 |
21 Jan 2013 to 15 July 2013 |
Valid |
|
GW-RS0241-13 |
11 Mar 2013 |
13 Mar 2013 to 10 Sept 2013 |
Valid |
|
GW-RS0251-13 |
11 Mar 2013 |
26 Mar 2013 to 24 Sept 2013 |
Valid |
|
GW-RS0340-13 |
28 Mar 2013 |
10 Apr 2013 to 8 Oct 2013 |
Valid |
|
GW-RS0373-13 |
9 Apr 2013 |
19 Apr 2013 to 17 Oct 2013 |
Valid |
|
GW-RS0437-13 |
26 Apr 2013 |
1 May 2013 to 29 Oct 2013 |
Valid |
|
GW-RS0155-13 |
15 Feb 2013 |
16 Feb 2013 to 14 Aug 2013 |
Valid |
|
GW-RS0269-13 |
23 Mar 2013 |
23 Mar 2013 to 19 Sept 2013 |
Valid |
|
GW-RS0467-13 |
6/5/2013 |
17/5/2013 to 16/11/2013 |
Valid |
|
GW-RS0517-13 |
20/5/2013 |
27/5/2013 to 26/11/2013 |
Valid |
|
GW-RS0521-13 |
20/5/2013 |
22/5/2013 to 21/11/2013 |
Valid |
|
GW-RS0530-13 |
20/5/2013 |
28/5/2013 to 27/11/2013 |
Valid |
|
GW-RE0508-13 |
21/5/2013 |
30/5/2013 to 29/11/2013 |
Valid |
|
GW-RS0525-13 |
21/5/2013 |
30/5/2013 to 29/11/2013 |
Valid |
|
GW-RS0538-13 |
21/5/2013 |
30/5/2013 to 29/11/2013 |
Valid |
|
GW-RS0539-13 |
23/5/2013 |
6/6/2013 to 5/12/2013 |
Valid |
|
GW-RS0554-13 |
23/5/2013 |
6/6/2013 to 5/12/2013 |
Valid |
|
GW-RS0586-13 |
27/5/2013 |
28/5/2013 to 22/11/2013 |
Valid |
|
GW-RS0633-13 |
14/6/2013 |
16/6/2013 to 13/12/2013 |
Valid |
|
Discharge
Licenses |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |
Cancelled |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
31 Jul 2015 |
Valid |
|
WT00008982-2011 |
26 April 2011 |
30 April 2016 |
Valid |
|
WT00009691-2011 |
1 Aug 2011 |
31 July 2016 |
Valid |
|
Billing Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table 3.7 Summary of submission status under FEP-01/364/2009
EP
Condition |
Submission |
Date of Submission |
Condition
2.7 and 2.8 |
Works Schedule and Location Plan |
14 Jun 2011 |
Condition
2.6 |
Environmental Management
Organization Chart |
14 Jun
2011 |
Condition
2.6 |
Commencement Date of Works |
21 Jun
2011 |
Condition 2.11 |
Landscape
Plan (Revision B) |
20 Nov 2012 |
Condition
2.9 |
Noise
Management Plan (Revision A) |
13 Jan 2012 |
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass
(CWB) ¡V Central Interchange under FEP-05/364/2009/A
3.1.7.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.8 and Table 3.9.
Table 3.8 Cumulative Summary of Valid Licences and Permits
under Contract no. HY/2009/18
Permit / Licence / Notification
/ Approval |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Permit issued |
Valid |
Notification of Works Under APCO |
322293 |
07 Oct 2010 |
Notified |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0396-13 |
16 Apr 2013 |
22 Apr 2013- 21 Oct 2013 |
Valid |
GW-RS-0459-13 |
30 Apr 2013 |
03 May 2013- 02 Nov 2013 |
Valid |
|
GW-RS1382-12 |
02 Jan 2013 |
04 Jan 2013 to 30 Jun 2013 |
Valid |
|
GW-RS0068-13 |
18 Jan 2013 |
05 Feb 2013 to 03 Aug 2013 |
Valid |
|
GW-RS0036-13 |
11 Jan 2013 |
23 Jan 2013 to 22 Jul 2013 |
Cancelled |
|
GW-RS1286-12 |
07 Dec 2012 |
11 Dec 2012- 05 Jun 2013 |
Cancelled |
|
Discharge Licence |
WT00012998-2012 |
25 May 2012 |
31 Jan 2016 |
Valid |
WT00013967-2012 |
17 Sep 2012 |
30 Sep 2017 |
Valid |
|
WT00014966-2013 |
08 Jan 2013 |
31 Jan
2018 |
Valid |
|
Registration as a Waste Producer |
WPN:
8335-121-L1048-04 |
17
Dec 2010 |
N/A |
Registration
completed |
Billing
Account under Waste Disposal Ordinance (Land) |
Account
No.: 7011587 |
11 Oct 2010 |
Account
approved |
Valid |
Table 3.9 Summary of submission status under
FEP-05/364/2009/A
EP
Condition |
Submission |
Date of Submission |
Condition
2.9 |
Noise
Management Plan |
01
March 2011 |
Condition
2.10 |
Landscape
Plan (Rev. 5) |
12
March 2012 |
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
3.1.8.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.10 and Table 3.11
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for
non-piling equipment |
GW-RS0434-13 |
23 Apr 2013 |
23 Apr 2013 to 16 Oct
2013 |
Valid |
GW-RS0588-13 |
31 May 2013 |
2 Jun 2013 to 26 Nov
2013 |
Valid |
|
GW-RS0601-13 |
31 May 2013 |
2 Jun 2013 to 29 Nov
2013 |
Valid |
|
GW-RS1191-12 |
26 Nov 2012 |
26 Nov 2012 to 11 May 2013 |
Cancelled |
|
GW-RS0038-13 |
17 Jan 2013 |
26 Jan 2013 to 25 Jul
2013 |
Cancelled |
|
GW-RS0087-13 |
24 Jan 2013 |
26 Jan 2013 to 20 July 2013 |
Valid |
|
GW-RS0399-13 |
18 Apr 2013 |
18 Apr 2013 to 10 Oct 2013 |
Valid |
|
GW-RS1345-12 |
21 Dec 12 |
24 Dec 12 to 23 Jun 2013 |
Cancelled |
|
GW-RS1342-12 |
21 Dec 2012 |
26 Dec 2012 to 25 Jun 2013 |
Valid |
|
GW-RS1391-12 |
8 Jan
2013 |
8 Jan 2013 to 24 Jun 2013 |
Cancelled |
|
GW-RS1257-12 |
4 Dec
2012 |
8 Dec 2012 to 7 Jun
2013 |
Cancelled |
|
GW-RS0175-13 |
25 Feb
2013 |
27 Feb 2013 to 13 Aug 2013 |
Valid |
|
GW-RS0306-13 |
26 Mar 2013 |
27
Mar 2013 to 22
Sep 2013 |
Valid |
|
GW-RS0276-13 |
19 Mar 2013 |
19
Mar 2013 to 7 Sep 2013 |
Cancelled |
|
GW-RS0231-13 |
6 Mar 2013 |
6
Mar 2013 to 21 Aug 2013 |
Cancelled |
|
GW-RS0217-13 |
28 Feb 2013 |
28
Feb 2013 to 30 Jun 2013 |
Valid |
|
GW-RS0463-13 |
6 May
2013 |
7 May 2013 to 6 Nov 2013 |
Valid |
|
Registration
as a Chemical Waste Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011553 |
30 Sep 2010 |
27
Sep 2010 to 27
Jan 2016 |
Valid |
Billing Account under Waste
Disposal Ordinance (Dumping by Vessel) |
7011761 |
10 Oct12 |
17
Jan
2013 to 16
Apr
2013 |
Valid |
Water Discharge License (TS1) |
WT00008780-2011 |
24 Nov 2011 |
24 Nov 2011 to 31 Mar 2016 |
Valid |
Water Discharge License
(Discharge at CHT area) |
WT00012941-2012 |
10 May 2012 |
10 May 2012 to 31 May 2014 |
Valid |
Water Discharge License
(Discharge at TPCWAE) |
WT00011322-2011 |
15 Dec 2011 |
15 Dec 2011 to 31 Dec 2013 |
Valid |
Water Discharge License
(Discharge at TS4) |
WT00011718-2012 |
16 Jan 2012 |
16 Jan 2012 to 31 Jan 2014 |
Valid |
Water Discharge License
(Discharge at TS2 |
WT00014974-2013 |
10 Jan 2013 |
10 Jan 2013 to 31 Jan
2015 |
Valid |
Table 3.11 Summary of submission status under FEP-06/364/2009/A
EP
Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management
Organization of Main Construction Companies |
11 Mar
2011 |
Amendment
for Management Organization of Main Construction Companies |
16 May
2011 |
|
Condition
2.7 |
Works
Schedule |
15 Mar
2011 |
Condition
2.8 |
Location
Plan |
15 Mar
2011 |
Condition
2.23 |
Noise
Management Plan |
6 May
2011 |
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
3.1.9.
The current status on licences and/or permits
on environmental protection pertinent and submission
under FEP-07/364/2009/A for contract no. HY/2009/19 are shown in Table 3.12 and Table
3.13
Table 3.12
Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/19
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
25 Feb 2011 |
N/A |
Valid |
|
Notification of Works Under APCO |
326160 |
24 Jan
2011 |
N/A |
Valid |
Registration as a Waste Producer |
7012306 |
10 Feb 2011 |
N/A |
Valid |
Registration as Chemical Waste
Producer |
5213-151-C3654-01 |
24 Mar 2011 |
N/A |
Valid |
Application for Vessel Disposal |
7012306 |
21 July 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) |
GW-RS0013-13 |
08 Jan 2013 |
07 Jul 2013 |
Valid |
GW-RS0503-13 |
20 May 2013 |
21 May 13- 20 Nov 13 |
Valid |
|
GW-RS0528-13 |
16 May 2013 |
26 May 13-25 Nov 13 |
Valid |
|
GW-RS0286-13 |
15 Mar 2013 |
15-Mar-12 to 14 -Sep-13 |
Cancelled |
|
GW-RS0046-13 |
18 Jan 2013 |
10 Jul 2013 |
Valid |
|
GW-RS0365-13 |
21 Apr
2013 |
21-Apr-13
to 20-Oct-13 |
Valid |
|
GW-RS0337-13 |
05 May 2013 |
05-May-13 to 01- Oct-13 |
Valid |
|
GW-RS1210-12 |
29 Nov 2012 |
29 Nov 12 to 28 May 13 |
Cancelled |
|
GW-RS0010-13 |
08 Jan 2013 |
08 Jan 12 to 07 Jul 13 |
Cancelled |
|
Water Discharge Licence |
WT00010093-2011 |
31-Aug-11 |
30-Sep-16 |
Cancelled |
WT00010093-2011 |
17-Aug-12 |
30-Sep-16 |
Valid |
|
WT00010865-2011 |
3-Nov-11 |
30-Nov-16 |
Valid |
Table 3.13
Summary of submission status under
FEP-07/364/2009/A
EP Condition |
Submission |
Date of
Submission |
Condition
2.13 |
Landscape
Plan |
16 March 2012 |
Condition
2.9 |
Noise
Management Plan (Rev.3) |
15 March 2013 |
Contract
no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over
MTR Tsuen Wan Line
3.1.10.
The current status on licences and/or permits on environmental protection
pertinent and submission under FEP-08/364/2009/A for contract no. HK/2010/06 showed in Table 3.14 and Table 3.15.
Table 3.14 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2010/06
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-08/364/2009/A |
15 June
2012 |
N/A |
Valid |
Notification of Works Under APCO |
326344 |
18 Jan 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) |
GW-RS0056-13 |
14 Jan
2013 |
16 Jan
2013 ¡V 12 Jul 2013 |
Valid |
Table
3.15 Summary of submission status under FEP-08/364/2009
EP
Condition |
Submission |
Date of Submission |
|
Acknowledgement
letter of FEP-08/364/2009A |
14
Aug 2012 |
Condition
2.9 |
Noise
Management Plan |
26 Nov 2012 |
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at
Wan Chai West
3.1.11
The current status on licences and/or permits on environmental
protection pertinent and submission under FEP-09/264/2009/B for contract no.
HK/2012/08 showed in Table 3.16 and Table 3.17
Table 3.16 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2012/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-09/364/2009/B |
5 March
2013 |
N/A |
Valid |
Notification of Works Under APCO |
355439 |
4 Feb 2013 |
N/A |
Valid |
Registration as a Chemical Waste
Producer |
5213-134-C3790-01 |
8 Mar 2013 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7016883 |
18 Feb 2013 |
18 Jul 2017 |
Valid |
Table 3.17 Summary of submission status under FEP-09/364/2009
EP Condition |
Submission |
Date
of Submission |
|
Acknowledgement letter of FEP-08/364/2009A |
14 Aug 2012 |
Condition 2.9 |
Noise Management Plan (Rev.1) |
27 May
2013 |
Condition 2.14 |
Landscape Plan (Rev.1) |
31 May
2013 |
Noise
Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are listed and shown in Table
4.1 and Figure 4.1.
Appendix 4.1 shows the established Action/Limit Levels
for the monitoring works.
Table
4.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun
Area |
M3a |
Tung Lo
Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
*M8 |
City Hall |
* Remark 1: Location ID has been updated from M7 to
M8 for City Hall
* Remark 2: M7e has become a reference station
starting from 7 Aug 2012
Real time Noise Monitoring
Stations
4.1.2.
Review of feasibility on the real time noise
monitoring stations was conducted in July with IEC. Station, RTN1a, Tung Lo Wan
fireboat Station was found not appropriate to be a monitoring station for
monitoring the IECL Piling works and Demolition after visited.
4.1.3.
The noise monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels
for the monitoring works.
Table 4.2 Real Time Noise Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD
Hong Kong Transport Section
Whitfield Depot |
North
Point |
RTN2a |
Electric Centre |
North Point |
RTN3 |
Po Leung Kuk Yu |
Tin Hau |
RTN4 |
|
Noise
Monitoring Parameters, Frequency and Duration
4.1.4.
The construction noise level shall be measured in
terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period between 0700 and 1900 hours on normal weekdays.
For all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
4.1.5.
Noise monitoring shall be carried out at all
the designated monitoring stations. The monitoring frequency shall depend on
the scale of the construction activities. The following is an initial guide on
the regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
¡P One set of measurements between 0700
and 1900 hours on normal weekdays.
4.1.6.
Real time noise shall be carried out at the
designated monitoring stations. The following is an initial guide on the
regular monitoring frequency for each station on a 24 hours daily basis when
noise generating activities are underway:
¡P One set of measurements between 0700
and 1900 hours on normal weekdays.
¡P One set of measurements between 1900
and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.
¡P One set of measurements between 2300
and 0700 hours on next day on everyday.
4.1.7.
If construction works are extended to include
works during the hours of 1900 ¡V 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring
Equipment
4.1.8.
As referred to in the Technical Memorandum ™
issued under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
4.1.9.
Noise measurements shall not be made in fog,
rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10
m/s. The wind speed shall be checked with a portable wind speed meter capable
of measuring the wind speed in m/s.
4.1.10.
The sound level meter shall be checked using
an acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit.
Measurements will be accepted as valid only if the calibration level from
before and after the noise measurement agree to within 1.0 dB.
Air Quality
Monitoring Stations
4.2.1.
The air monitoring stations for the Project
are listed and shown in Table 4.3 and Figure 4.1.. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil
Street Site Office** |
North Point (Re-commenced on 14 November 2011) |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society
for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
|
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (western End of Podium) |
Central |
Remarks*: As
per the ENPC meeting in March 2011, the monitoring stations CMA3a ¡V Future CWB
site office at Wanchai Waterfront Promenade was renamed as remark.
Remarks**: The
location ID of monitoring station CMA1b was updated as ¡§Oil Street Site Office¡¨
in April 2013.
Air Monitoring
Parameters, Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling
Procedure and Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance
with the following specifications shall be used for carrying out the 1-hour and
24-hour TSP monitoring:
¡P 0.6 ¡V 1.7 m3 per minute adjustable
flow range;
¡P Equipped with a timing / control device
with +/- 5 minutes accuracy for 24 hours operation;
¡P Installed with elapsed-time meter with
+/- 2 minutes accuracy for 24 hours operation;
¡P Capable of providing a minimum exposed
area of 406 cm2;
¡P Flow control accuracy: +/- 2.5%
deviation over 24-hour sampling period;
¡P Equipped with a shelter to protect the
filter and sampler;
¡P Incorporated with an electronic mass
flow rate controller or other equivalent devices;
¡P Equipped with a flow recorder for continuous
monitoring;
¡P Provided with a peaked roof inlet;
¡P Incorporated with a manometer;
¡P Able to hold and seal the filter paper
to the sampler housing at horizontal position;
¡P Easily changeable filter; and
¡P Capable of operating continuously for a
24-hour period.
4.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly
intervals. The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference.
All the data should be converted into standard temperature and pressure
condition.
Laboratory
Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
Filter paper of size 8¡¨ x 10¡¨ shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
4.2.9.
After sampling, the filter paper loaded with
dust shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
4.2.10.
All the collected samples shall be kept in a
good condition for 6 months before disposal.
4.2.11.
Current calibration certificates of
equipments are presented in Appendix
4.2.
5.0.1.
The environmental monitoring will be
implemented based on the division of works areas of each designated project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing
work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure
2.1 and Figure 4.1. The monitoring results are
presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent
contracts are as follows:
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
Contract no.
HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under
FEP-05/364/2009/A
Contract no.
HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link under
FEP-07/364/2009
Contract no.
HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Contract no.
HK/2009/02 - Wan Chai Development Phase II ¡V Central - Wan Chai Bypass at Wan
Chai East
Contract no.
HK/2010/06 - Wan Chai Development Phase II ¡V Central - Wan Chai Bypass over MTR
Tsuen Wan Line
Contract no.
HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan
Chai West
5.0.3.
The environment monitoring schedules for
reporting month and coming month are presented in Appendix 5.1.
5.1.1 Due to adverse weather condition, the
noise monitoring at the following stations were rescheduled:
M1a and
M2b: From 11 June 2013 to 14 June 2013
M3a, M4b
and M5b and M6: From 11 June 2013 to 13 June 2013
5.1.2
Monitoring for report of review baseline noise
level was performed from 11 April 2011 to 8 June 2011. Then the report was submitted on the 20
June 2011, verified by IEC on 18 July 2011 and was approved by ER by January
2012. The new baseline is used for
the noise calculation starting from January 2012.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
5.1.3 Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2009/18 are summarized in Table 5.2 below:
Table
5.2
Noise Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of
Podium) |
M7w |
International Finance Centre (Western End of
Podium) |
M8 |
City Hall |
* Remark:
M7e has become a reference station starting from 7 Aug 2012
5.1.4 One action level exceedance regarding
noise complaint concerning location near Central Pier area was received by ET
on 11 June 2013. After investigation, no non-compliance was identified.
5.1.5
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre ¡V Tunnel Works under FEP-02/364/2009 and Contract no.
HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
5.1.6
The commencement of construction works for
Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and
HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of
noise monitoring stations are summarized in Table 5.3 below.
able
5.3
Noise Monitoring
Station for Contract
no HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.7
No action or limit level exceedance was recorded
in this reporting month.
5.1.8
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (
5.1.9 The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise
monitoring was commenced on 13 July 2011. The proposed divisions of
noise monitoring stations are summarized in Table 5.4 below.
Table
5.4 Noise Monitoring Stations for Contract
no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.10
No action or limit level exceedance was
recorded in this reporting month.
5.1.11
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
5.1.12 Noise monitoring for the
tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The
proposed division of noise monitoring stations are summarized in Table
5.5 below.
Table
5.5
Noise Monitoring Stations
for Contract
no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
5.1.13
Two limit level
exceedances were recorded on 3 and 13 June 2013 at M6 ¡V HK Baptist Church Henrietta
Secondary School in the reporting month.
5.1.14
Major traffic noise observed during monitoring
on 3 and 13 June 2013 and it was considered as the major noise contribution. As
such, the limit level exceedances were concluded as non-project related.
5.1.15
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2. Details
of the Notification of Exceedance can be referred in Appendix 6.2.
5.2.1.
As confirmed by CWB RSS, the IECL parapet removal operations and
associated construction work will commence in June 2013. Liaison was conducted with HK Baptist
Church Henrietta Secondary School, Po Leung Kuk Yu Lee Mo Fan Memorial School and
Causeway Bay Community Centre regarding the set up of RTN3 real time noise
monitoring station.
5.2.2.
5.2.3.
Real time noise monitoring at RTN4-Causeway Bay Community Centre was
commenced on 13 Jan 2013.
5.2.4.
Po Leung Kuk Yu Lee Mo Fan Memorial School grant permission for set up
on 4 Sep 2012 and station set up was performed on 14 Sep 2012. Real time noise
baseline capturing was conducted during time period without construction work
from 21 Sep 2012 to 04 Oct 2012.
5.2.5.
Real time noise monitoring at RTN3 ¡V Po Leung Kuk Yu Lee Mo Fan Memorial School was commenced
since 06 Oct 2012.
5.2.6.
Oil Street Community Liaison Centre was confirmed to be demolished in
mid-October by CWB RSS. This
presented a need for relocation of RTN2 ¡V Oil Street Community Liaison
Centre. After liaison with Hong
Kong Electric, permission was granted on 21 Sep 2012 for real time noise
monitoring set up at City Garden Electric Centre (RTN2a ¡V Electric Centre),
which is a representative of the noise sensitive receiver City Garden.
5.2.7.
RTN2 previously located at oil Street Community Liaison Centre was
relocated to Hong Kong Electric Centre on 5 Oct 2012, which is a representative
of the noise sensitive
5.2.8.
Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely
adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with
respect to the commencement of advance works for IEC parapet demolition.
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
5.2.9.
The proposed division of noise monitoring
stations are summarized in Table 5.7 below. Real time noise
monitoring for major construction works under contract no. HY/2009/19 was
commenced on 24 April 2011.
Table
5.7 Real Time Noise
Monitoring Stations
for Contract
no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section
Whitfield Depot |
RTN2a |
North
Point |
Electric Centre |
RTN3 |
North
Point |
Po Leung Kuk Yu |
RTN4 |
Tin
Hau |
|
* Real time noise monitoring results and graphical presentation during
night time period are for information only.
*Real-time noise monitoring results and graphical presentation for RTN3
during restricted hours are for information only as no night classes were
conducted at the educational institute.
5.2.10.
Limit level exceedances were recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot during restricted hours
on 15 June 2013. After checking with contractor, no major noisy construction
works with only one mobile crane was in operation at the concerned location
during the recorded period. As such, the exceedances were considered not
contributed by the project works but due to the nearby IEC traffic.
5.2.11.
Limit level exceedance was recorded at
RTN2a-Electric Centre during restricted hours on 4 June 2013. After checking
with contractor, no construction work was conducted 4 June 2013 at the
concerned location during the recorded period. As such, the exceedances were
considered to be contributed by near by IEC traffic.
5.2.12.
No limit Level exceedance was recorded at
RTN3-Yu Lee Mo Fan Memorial School in the reporting month.
5.2.13.
No limit level exceedance was recorded at
RTN4-Causeway Bay Community Centre in the reporting month.
5.2.14.
Real time noise monitoring results measured
in this reporting period are reviewed and summarized. Details of real time
noise monitoring results and graphical presentation can be referred to Appendix 5.4.
5.3.1
Due to interruption of electricity supply,
the 1hr TSP monitoring at CMA5a was rescheduled from 22 June 2013 to 24 and 25
June 2013.
5.3.2
24hr TSP monitoring at CMA5a scheduled on 21
June 2013 as temporarily suspended due to continuous electricity power supply
for 24hrs was unavailable.
Contract no. HY/2009/18 ¡V
Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
5.3.3
Air monitoring for the Central Interchange
works under contract no. HY/2009/18 was commenced on 21 April 2011. The
proposed division of air monitoring stations are summarized in Table 5.9
below.
Table 5.9
Air
Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of
Podium) |
MA1w |
International Finance Centre (Western End of
Podium) |
5.3.4
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air monitoring results and graphical
presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
5.3.5
The commencement of construction works for
Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality
monitoring was commenced on 25 August 2011. The proposed division of air
monitoring stations are summarized in Table 5.10 below.
Table
5.10
Air
Monitoring Station for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
5.3.6
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of
air monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
5.3.7
The commencement of construction works for
HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of
air monitoring stations are summarized in Table 5.11 below.
Table
5.11
Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
5.3.8
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of
air monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (
5.3.9
The commencement of construction works for
Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Air
quality monitoring was commenced on 14 July 2011. The proposed division of air monitoring stations are summarized in Table
5.12 below.
Table
5.12 Air Monitoring Station for Contract
no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.10
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of
air monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
5.3.11
The proposed division of air monitoring
stations are summarized in Table 5.13 below. Air monitoring for
the tunnel works under contract no. HY/2009/19 was commenced on 26 April 2011.
Table
5.13
Air Monitoring
Stations
for Contract
no. HY/2009/19
Station |
Description |
CMA1b |
Oil Street Site Office |
CMA2a |
|
5.3.12
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of
air monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
5.4.1.
Inert C&D wastes and non-inert C&D wastes were disposed in this
reporting month. Details of the waste flow table are summarized in
Table 5.15.
Table 5.15 Details of Waste Disposal for Contract no. HK/2009/01
Waste Type |
|||
Inert C&D materials disposed |
1547.4 |
29358.245 |
TKO137, TM38 |
Inert C&D materials recycled |
Nil |
5104.5 |
N/A |
Non-inert C&D materials disposed |
29.66 |
1303.16 |
SENT Landfill |
Non-inert C&D materials recycled |
Nil |
205943 |
N/A |
Chemical waste disposed |
200 |
9750 |
N/A |
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
5.4.2.
Inert C&D & non-inert C&D wastes
were disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.16.
Table 5.16 Details of Waste Disposal for
Contract no. HK/2009/02
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Remarks |
Inert C&D materials disposed, m3 |
506.03 |
237062.97 |
TKO137 / TM 38 |
N/A |
Inert C&D materials recycled, m3 |
Nil |
18161 |
n/a |
N/A |
Non-inert C&D materials disposed, m3 |
45.49 |
967.68 |
SENT Landfill |
N/A |
Non-inert C&D materials recycled, m3 |
N/A |
N/A |
N/A |
N/A |
Chemical waste disposed, kg |
Nil |
7971 |
SENT Landfill |
N/A |
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass
(CWB) ¡V Central Interchange under FEP-05/364/2009/A
5.4.3.
Inert C&D and non-inert C&D waste was
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.17.
Table 5.17 Details of Waste Disposal for Contract
no. HY/2009/18
656 |
94671 |
||
234 |
56223 |
||
13 |
1173 |
||
0.03 |
77.87 |
||
3565 |
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
5.4.4.
Inert & Non-inert C&D wastes were disposed of in this reporting
month. Details of the waste flow table are summarized in Table 5.18.
Table 5.18 Details of Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this month(m3) |
Cumulative Quantity-to-Date(m3) |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
18696.8 10088.7 |
352670.1 207278.3 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials recycled, m3 |
Nil |
217596.2 |
HY/2009/11 ex-PCWA TS4 TS2 WDII Lun Ku Tan |
Non-inert C&D materials disposed, m3 |
53.7 |
862.7 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
45 |
543045.8 |
Xun Xiang Metalware
Skylight Recycle (paper) |
Chemical waste disposed, kg |
272 |
17483 |
Dunwell Group |
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
5.4.5.
Inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are summarized
in Table 5.19.
Table 5.19 Details of Waste
Disposal for Contract no. HY/2009/19
Inert
C&D materials disposed |
4342.25 |
299458.96 |
N/A |
Inert
C&D materials recycled |
4737.63 |
54001.81 |
N/A |
Non-inert
C&D materials disposed |
24.13 |
851.92 |
SENT Landfill |
Non-inert
C&D materials recycled |
15.49 |
297.52 |
N/A |
Chemical
waste disposed |
Nil |
4.59 |
N/A |
Contract no.
HK/2010/06 Wan Chai Development Phase II - Central-Wan Chai Bypass over MTR
Tsuen Wan Line under FEP-08/364/2009/A
5.4.6.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.20.
Table 5.20 Details of Waste Disposal for Contract
no. HK/2010/06
Inert C&D materials disposed |
NIL |
NIL |
TM38 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
Recyclers |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract no.
HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai
West under FEP-09/364/2009/B
5.4.7.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.21.
Table 5.21 Details
of Waste Disposal for Contract no. HK/2012/08
Waste Type* |
Quantity this month, m3 |
Cumulative-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
6.0.1.
The Event Action Plan for construction noise,
air qualities are presented in Appendix 6.1.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
6.1.1
One action level exceedance regarding noise complaint concerning
location near Central Pier area was received by ET on 11 June 2013. After
investigation, no non-compliance was identified.
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at
6.1.1. No exceedance
was recorded in the reporting month.
Contract no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.1.2. No exceedance
was recorded in the reporting month.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V
Tunnel (
6.1.3. No exceedance
was recorded in the reporting month.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
6.1.4.
Two limit level
exceedances were recorded on 3 and 13 June 2013 at M6 ¡V HK Baptist Church Henrietta
Secondary School in the reporting month. Investigations found that on 3 and 13 June 2013, major traffic
noise was contributed in the noise monitoring and exceedances were not related to the
Project.
Real Time Noise Monitoring
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.1.6. Non project
related limit level
exceedance was recorded at RTN2a- Electric Centre on 4 June 2013. Investigation
found that exceedances were contributed by IEC traffic.
6.1.7. No limit level
exceedance was recorded at RTN3- Yu Lee Mo Fan Memorial School in this
reporting month.
6.1.8. No limit level exceedances
were recorded at RTN4- Causeway Bay Community Centre in this reporting month.
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass
(CWB) ¡V Central Interchange under FEP-05/364/2009/A
6.2.1.
No exceedance was recorded in the reporting
month.
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at
6.2.2.
No exceedance was recorded in the reporting
month.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
6.2.3.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V
Tunnel (
6.2.4.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.2.1
No exceedance was recorded in the reporting
month.
6.3.1.
There was no non-compliance from the site
audits in the reporting period. The observations and recommendations made in
each individual site audit session were presented in Section 8.
6.3.2.
No project-related non-compliance from
monitoring was recorded in the reporting month.
7.0.1.
According to Condition 3.4 of the
EP-364/2009/B, this section addresses the relevant cumulative construction
impact due to the concurrent activities of the current projects including the
Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB
Tunnel).
7.0.2.
According to the Monthly EM&A report (May
2013) of Central Reclamation Phase III (CRIII), Underground drainage
and footpath construction, modification to the junction of Road D8 and Road P2 and
modification of timber decks at advance promenade were performed in the June
2013 reporting month. The water quality monitoring was completed in
October 2011 and no Project-related exceedance was recorded for air and noise
monitoring. It can be concluded
that cumulative construction impact due to the concurrent activities of the
current projects with the Central Reclamation Phase III (CRIII) was
insignificant.
7.0.3.
According to the construction programme of
Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern
Corridor Link projects, the major construction activity under Wan Chai
Development Phase II were marine works at HKCEC areas, cross-harbour
Watermains, Fresh Watermains and Cooling Watermains Installations, tunnel works
at Wan Chai East, ELS work at TS4 and deep excavation at
TPCWAE TCBR1W. Excavation and tunnel works at Central Interchange, ELS and box
culvert construction at North Point area. The major environmental impact was
water quality impact at
7.0.4.
The major environmental impacts generated
from tunnel works at Central and tunnel works at Wan Chai East, IECL and
Causeway Bay Typhoon Shelter were undertaken in the reporting month. No
significant air impact from construction activities was anticipated in the
reporting month. Besides, no project-related exceedances were recorded during
the air and noise environmental monitoring events in the reporting month. Thus,
it is evaluated that the cumulative construction impact from the concurrent
projects including Wan Chai Development Phase II was insignificant.
8.0.1.
During this reporting month, weekly
environmental site audits were conducted for Contracts no. HY/2009/15,
HY/2009/18, HY/2009/19, HK/2012/08, HK/2009/01, HK/2009/02 and HK/2010/06. No
non-conformance was identified during the site audits. The Contractors rectified major
observations and recommendations made during the audit sessions. No
non-conformance was identified during the site inspections.
8.0.2.
Five site inspections for Contract no.
HY/2009/15 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.1.
Table 8.1 Summary of Environmental
Inspections for Contract no. HY/2009/15
Date |
Item |
Observations |
Action taken by Contractor |
Outcome |
130528_01 |
28-May-13 |
Clear the leaked oil and provide proper container for oil storage |
Tarpaulin sheet was provided at the transfer location. |
Completion as observed on 04 June 2013. |
130604_01 |
4-Jun-13 |
Provide covering for material stockpile |
Covering was provided to stockpile |
Completion as observed on 11 June 2013 |
130611_01 |
11-Jun-13 |
Surface overflow observed along seawall. The contractor is
recommended to review and provide contingency measures to minimize the
surface overflow of construction effluent during rainstorm. |
Mitigation measures were implemented during rainstorm to minimize
surface runoff |
Completion as observed on 18 June 2013 |
130618_01 |
18-Jun-13 |
Clear the temporary drainage channel to avoid blockage which
would impair flow (TS2) |
The condition of the
temporary drainage channel was improved/ |
Completion as observed on 2 July 2013 |
130618_02 |
18-Jun-13 |
Clear the mud residue resting at the edge of the barge to prevent
drop off into the sea and provide tarpaulin sheet during transfer (TS2) |
Tarpaulin sheeting was provided during transfer |
Completion as observed on 2 July 2013 |
130625_01 |
25-Jun-13 |
Seepage of muddy water with grease through the seawall (TS2
northern side) |
No further muddy seepage was observed |
Completion as observed on 2 July 2013 |
8.0.3.
Four site inspections for Contract no.
HY/2009/18 was carried out during this reporting period. The results of these inspections and outcomes
are summarized in Table 8.2.
Table
8.2 Summary
of Environmental Inspections for Contract no. HY/2009/18
Date |
Item |
Observations |
Action taken by Contractor |
Outcome |
130606_01 |
6-Jun-13 |
The tree near the Gate 6 should be properly fence off. |
The area was found not occupied by the
contractor. |
Completion as observed on 13 Jun 2013 |
130606_02 |
6-Jun-13 |
The discharge at Portion VI near |
No further milky discharged was
observed |
Completion as observed on 13 Jun 2013 |
8.0.4.
Four site inspections for Contract no.
HY/2009/19 was carried out during this reporting period. No observation
was found in the reporting month.
8.0.5.
Five site inspections for Contract no.
HK/2009/01 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.3
Table
8.3 Summary of Environmental
Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
130605_01 |
5-Jun-13 |
Drip tray should be provided for chemical containers, or chemical
container should be clean as chemical waste. (Water channel) |
Drip tray was provided |
Completion as observed on 13 Jun 2013 |
130613_01 |
13-Jun-13 |
Wheel washing should be applied to prevent leading mud to the
public haul road.(Expo Drive Middle) |
Mud trail observed as cleared |
Completion as observed on 20 Jun 2013 |
130613_02 |
13-Jun-13 |
Grouting station should be properly 3- side enclosed and top enclosed |
3 side and top enclosures were provided to grouting station. |
Completion as observed on 20 Jun 2013 |
130620_01 |
20-Jun-13 |
Oil stain was found, oil should be prevent from leakage( |
Oil stain was removed. |
Completion as observed on 26 Jun 2013 |
130620_02 |
20-Jun-13 |
Chemical container should be properly stored or cleared (Water
Channel) |
Chemical container have been removed |
Completion as observed on 26 Jun 2013 |
8.0.6.
Five site inspections for Contract no.
HK/2009/02 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.4
Table 8.4 Summary of Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
130606_01 |
6-Jun-13 |
Floating rubbish should be cleared more frequently(WCR1) |
Floating refuses were cleared |
Completion as observed on 13 June 2013 |
130613_01 |
13-Jun-13 |
Oil leakage was observed. Oil should be prevented from leakage
and oil leakage should be clear as chemical waste.(WCR II) |
Oil stain have been removed and cleaned |
Completion as observed
on 19 June 2013 |
8.0.7.
Five site inspections for Contract no.
HK/2010/06 was carried out during this reporting period. No observation was
found in the reporting month.
8.0.8.
Five site inspection for Contract no.
HK/2012/08 was carried out during this reporting period. No observation was
found in the reporting month.
9.0.1.
Two environmental complaints under
FEP-05/364/2009/A were received in the reporting period.
9.0.2.
One environmental complaint under
EP-364/2009/B was received on 6 June 2013 (ICC Ref: No: #1-430164728 dated 30
May 2013) regarding landscape aspect along
A follow-up joint inspection with RSS and
Landscape specialist was conducted on 10 June2013, it was considered that the
withered and yellow leaves of the affected trees
(T1674,T1675,T1676,T1677,T1678,T1679,T1680,T1681,T1683,T1644,T1643,T1641,T1639)
at the concerned planter area were contributed by natural life cycle of the
affected trees and the health condition of the affected trees were considered
to be fair. It was also noted that an active CEDD works area was located within
the concerned planter area in close proximity to few of the concerned trees
(T1644, T1643, T1641, and T1639)
According
to tree inspection records from Jan 2013 to May 2013 confirmed by RSS (Document
Ref: CI-F1-043b, CI-F1-044b, CI-F1-045b, CI-F1-046b, CI-F1-047b), the affected
tree (T1712) at the concerned planter area was considered to show sign of
withering and considered to be in poor health condition in latest tree survey
report confirmed by RSS.
During
the follow-up inspection on 10 June 2013, it was observed those construction
material and oil drums were placed near the roots area of other trees within
the CEDD works. Despite the above observation, no direct evidence was found on
site which indicates the work front have contributed to the poor health
condition of the affected tree (T1712) at the time of investigation.
Nevertheless,
regular inspection to check the health condition of the trees and regular
removal of withered leaves or dead branches which deemed appropriate to
maintain the overall tree appearance were implemented by the contractor.
One environmental
complaint under EP-364//2009/B was received on 11 June
2013 (EPD Ref.:H04/RS/00011587-13) dated 11 June 2013) regarding noise impact
near Central Piers in the reporting month.
The
complainant reported that the noise was emanated from the construction site
near the Central Piers at around 0900 hrs on 30 May 2013 and other days and
requested follow up action by relevant department. RSS confirmed that major
noise generating construction activities undertaken at works area near Central
Pier during the concerned time include breaking up existing D-wall concrete and
excavation at portion 4B, 4C and sheet pilling works at Portion VI (
Total 1
no. of Backhoe with breaker, 1 no. of Backhoe with vibratory hammer and 4 no.s
of pneumatic breakers were deployed for the above construction activities.
Reviewing
the noise monitoring data at monitoring stations (M7e- International Finance
Centre Eastern End of Podium and M7w- International Finance Centre Western End
of Podium), no limit level exceedances were recorded during routine noise
monitoring event on 28 May 2013 and 03 June 2013. As similar construction works
activities conducted on 30 May 2013 was continued across the above monitoring
period, the noise emanated from the construction activities under Contract
HY/2009/18 was considered complied with the statutory requirement.
In
addition, weekly environmental site inspection was conducted on 30 May 2013 at
around 10:00. According to the inspection record, no particular observation
regarding noise impact was recorded and the mitigation measures including
erection of temporary noise barrier was observed in place.
Nevertheless, the
contractor was recommended to review the need of additional noise mitigation
measures to further reduce the noise emanated during construction works for
pier side public area.
9.0.3.
The details of cumulative complaint log and updated summary of
complaints are presented in Appendix
9.1
9.0.4. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table 9.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
June 2013 |
2 |
Sep 2010 ¡V May 2013 |
20 |
Total |
22 |
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month
(Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1.
The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2.
The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1. The construction programmes of individual contracts are provided
in Appendix 10.1.
Table
10.1 Summary of Key Construction Activities of Individual Contract(s)
to be commenced in Coming Reporting Month
Contract No. |
Key Construction
Works |
Recommended Mitigation Measures |
HY/2009/15 |
¡P
ELS works and pipe roofing works at TS4 ¡P
Cut and cover tunnel construction at
TPCWAE ¡P
Construction of OHVD at TS1 ¡P
Excavation for mined tunnel ¡P
Construction of Diaphragm Wall and
Installation of King Post at TS2 |
¡P
Watering any dust generating activities ¡P
Well maintained enclosures for grouting mixing plants. ¡P
Noise control measures shall be provided during restricted hours ¡P
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the sea |
HY/2009/18 |
¡P
Excavation of trial pit ¡P
Transplanting of trees ¡P
Hoarding erection and modification ¡P
Installation of couplers, UU detection, trial trench, pre-drilling ¡P
Excavation ¡P
Drainage works ¡P
Tunnel works ¡P
Trough structure construction and associated drilling and grouting ¡P
Road works ¡P
OHVD installation ¡P
Bridges construction ¡P
Scaffolding / false-work erection ¡P
Profile barrier construction |
¡P
Noise barrier shall be implemented; and ¡P
Noise level shall be controlled by reducing piling rate and no. of
plants working in parallel. ¡P
Dust control during dust generating activities ¡P
Provide protection works to ensure no runoff out of site area or
direct discharge into public drainage system. ¡P
Appropriate plants and measures should be taken to ensure adequate
protections are provided for trees being transplanted. |
HY2009/19 |
¡P
Road works at ¡P
Bored piling (Land) ¡P
D-wall and Barrette Construction ¡P
Construction works for Box Culvert T1 ¡P
Construction works for Culvert U1 ¡P
Construction of Pile cap (Land) ¡P
Demolition of parapet at IEC Link ¡P
Construction of dewatering well for Cut & Cover Tunnel ¡P
Removal of marine platform ¡P
Construction of pile cap, column & cross head (Marine) ¡P
ELS for Cut & Cover Tunnel ¡P
Laying of 1500 pipe ¡P
Launching of segments ¡P
Unloading segments from derrick ¡P
Extraction of temporary pile from marine section |
¡P
Noise level shall be controlled by reducing the breaking operation
rate. ¡P
Noise barrier shall be implemented. ¡P
Dust control during dust generating works ¡P
Provide protection works and adequate drainage system to ensure no direct
discharge into public drainage system or the sea. |
HK2009/01 |
¡P
Installation of pre-bored H-pile in CWB Stage 1B under the atrium
link (from Ch80 to Ch220) ¡P
Installation of pre-bored H-pile in CWB Stage 1B under the atrium
link (from Ch120 to Ch220) ¡P
Construction of bulkhead Wall at Ch3129 ¡P
Demolition of the promenade deck and pumping stations at HKCEC Water
Channel ¡P
Installation of dewatering well at CWB |
¡P
Noise level shall be controlled by reducing no. of plants working in
parallel. ¡P
Well maintained enclosures for grouting mixing plants. ¡P
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the sea. ¡P
Dust control during dust generating works |
HK/2009/02 |
¡P
Construction of Eastern Bulkhead wall. ¡P
Wall construction at Tunnel Portion 1. ¡P
D-Wall construction at Tunnel Portion 2. ¡P
Rock filling and leveling stone installation for seawall construction
at both WCR4 & TWCR4. ¡P
Geotextile installation for temporary reclamation at TWCR4 ¡P
Precast concrete seawall installation at WCR4 & TWCR4. ¡P
Continue backfilling and road reinstatement works at Hung Hing Road
& Wan Shing Street for successful implementation of HHR Flyover
Diversion (Stage 1) ¡P
Complete water plug
construction works at Bay5/Bay6 interface and commence construction of Bay 5
Box Culvert N1. |
¡P
Dust control during dust generating works ¡P
Provision of protection to ensure no runoff out of site area or
direct discharge into public drainage system. |
HK/2010/06 |
¡P
Installation works of Precast Concrete Box Unit ¡P
Remaining works in box unit (Installation of foam concrete) |
¡P
Dust control during dust generating works. |
HK/2012/08 |
¡P
Hoarding erection |
¡P
Dust control during dust generating works ¡P
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system. |
10.0.3.
The construction works of Contract no.
04/HY/2006 ¡V Reconstruction of Bus Terminus near
10.0.4.
The construction works of Contract no.
HY/2009/17 - Advance piling works at Whitfield Depot under FEP-03/264/2009 was
completed, and the FEP was surrendered by the Contractor and found in order by
EPD on 25 April 2013.